Back to list
ECHO
‘Our production
speed rose by forty percent while our energy cost halved.’
Floor elements have been manufactured at Echo
since 1954. The company called on Encon to optimise its production process. Its
know-how was also used for the construction of new production lines.
Echo has developed and produced floor elements for the construction sector
since 1954. This Limburg family firm has grown over more than half a century
into a leading player at the global level. Echo is even the market leader in
Belgium and the surrounding countries. Today the group employs more than seven
hundred people in over ten facilities. The step towards manufacturing
pre-stressed and reinforced concrete has been taken over the years, with the
help of new production methods and machines. During the manufacture of
pre-stressed hollow-core slabs, concrete is poured onto a so-called ‘production
bed’: a steel construction that can be compared with a long bowling alley. The
concrete elements are then heated on this bed to accelerate hardening. As soon
as the hollow-core slabs are sufficiently hardened, they are taken from the
production bed and stored. The production line is then prepared again for the
next cycle.
Echo started the construction of a new production unit in Genk in November
2008. This facility was to have four production beds (each 180 metres long and
2.7 metres wide). Encon was called in to analyse and optimise the energy
consumption of the existing process in the Houthalen facility in an initial
phase. This expertise then had to be applied to the new production lines. The
aim here was to reduce production costs to a minimum. ‘We were looking for a
method to heat our production beds as efficiently as possible,’ says Jorg
Pollaris. He is the technical innovation engineer at Echo and was closely
involved in the entire operation. ‘Among other things the optimum speed for the
hardening of our hollow-core slabs had to be investigated. Of course, we had to
call in experts for this. We selected Encon because of their good references.’
SIMULATION PROGRAM

The Encon engineering team started by mapping
the energy costs of the existing production process. The techniques used were
also compared with alternative methods for manufacturing concrete hollow-core
slabs. It quickly emerged that the bed heating was the biggest energy consumer
in the production process. In cooperation with Echo, Encon developed a special
simulation program that can simulate heat consumption in various circumstances.
‘Among other things these simulations helped with the choice of the most
suitable energy source: gas, fuel oil or electricity,’ says Pollaris.
‘Moreover, the simulation program taught us what the optimum heating bed
construction was. It quickly became clear from all of this that cogeneration
was the recommended technology for our production units.’
Echo also called Encon in to study and optimise the production speed. A
thorough analysis was performed again based on the simulation program.
Incidentally, to do this the Encon engineers cooperated with Echo Engineering,
a division of the Echo group which develops production machines. To lend weight
to the theoretical results of the simulation and to optimise these, extensive
measurement campaigns were then also carried out on the existing production
lines.
TRIAL DEPLOYMENT
Encon then built a trial deployment of a
production line with a usable surface area of one square metre. This enabled
the engineers to imitate the production process while simultaneously measuring
the temperature profile and energy consumption. To do this the trial deployment
was equipped with more than twenty temperature and power loggers. Various measurement
campaigns were carried out with different heating settings in each case.
Practical conclusions were drawn based on the measurement campaigns on the
existing production lines and measurements on the trial deployment. The optimum
settings for energy consumption and production speed were then determined based
on practical simulations. And to good effect: energy consumption has halved
today while the production speed has increased by more than forty percent. In
fact it is unbelievable how much money and energy you can save if you allow
energy specialists get involved in thinking about the development of your
production process.
After the positive results of the simulations, Encon carried out the
engineering to heat the production beds. The analyses had revealed that
cogeneration is the most energy-saving solution for this. However, it is
important for a cogeneration plant of this type to be dimensioned correctly. An
over sized installation would be detrimental to profitability, whereas an
installation that is too small would not lead to the proposed saving. However,
the work hall was still being built at the time. This meant that it was
impossible to dimension an existing installation with the help of measurement
campaigns. So it was decided to equip the new facility with natural-gas heating
boilers in a first phase. However, all steps were taken to allow the
integration of a cogeneration plant later. A heat meter was installed at the
time so that the system could be adjusted correctly later. This means that
sufficient measurement data should be available after approximately six months
of production to dimension the cogeneration system correctly.
ENGINEERING IN 3D
Encon then
designed the entire heating plant. During this engineering phase Encon created
a detailed design in which all of the components were drafted. This resulted in
a detailed three-dimensional plan. Jorg Pollaris: ‘The advantage of such a 3D
diagram is that it reveals possible practical difficulties during construction
in advance so that we can resolve these before everything is actually built.
Based on the full file, a set of specifications was then drawn up with an
invitation to quote for fitting the entire installation. Despite the complexity
of this project the full analysis and engineering were implemented in a period
of less than six months.’ Echo Engineering was responsible for the ultimate
construction of the new production lines.